Lead-time accuracy beats lead-time speed. A supplier promising 15 days with ±2 days variance is worth more than one promising 10 days with ±10 days variance, because your production plan is built on the certainty, not the average. Most scorecards weight lead time as “shorter is better.” That is wrong, and it is the single most common scoring error in procurement templates.

Below is the 23-check card, weighted, with the scoring rules that make it useful.

Weighting

CategoryWeightChecks
Quality system25%6
Certification25%5
Delivery20%5
Commercial15%4
Service15%3

Pass threshold: 70 / 100. Below 60, do not sample. 60–70, sample and re-audit.

Quality System — 25% (6 checks)

#CheckScore
1Burn-in coverage: 100% (5) / AQL sampled (3) / none (0)/5
2Burn-in duration ≥4 h @ 45°C (4) / 2 h (2) / none (0)/4
3Burn-in failure rate logged and <0.3% (5) / logged >0.3% (3) / not logged (0)/5
4Capacitor brand named, 105°C/10,000 h (5) / 105°C/2,000 h (2) / unbranded (0)/5
5Hi-pot 100% at 3,000 V AC (3) / AQL (2) / none (0)/3
6Serial traceability to component lot (3) / to batch (2) / none (0)/3

Certification — 25% (5 checks)

#CheckScore
7Certificate verified on issuing body’s website, in scope (6) / PDF only (2) / expired (0)/6
8Certificate covers your target market (5) / partial (2) / no (0)/5
9Holder named, and your rights on termination defined (5) / unclear (2)/5
10EMC and safety both covered (5) / safety only (2)/5
11Test report (not just certificate) available (4) / no (0)/4

A note on check 7: verify independently. Both TÜV and Intertek maintain online certificate databases. A PDF is trivially edited; the database is not.

Delivery — 20% (5 checks)

#CheckScore
12Lead time quoted with a stated variance (4) / point estimate (1)/4
13Variance ≤ ±3 days (5) / ±3–10 days (3) / >±10 days (0)/5
14On-time rate for last 12 months ≥95% (5) / 85–95% (3) / <85% (0)/5
15Sample lead time ≤15 days (3) / 15–30 (2) / >30 (0)/3
16Capacity buffer for a 2× order (3) / no (0)/3

Commercial — 15% (4 checks)

#CheckScore
17MOQ stated clearly, no hidden setup fee (4) / fees appear later (0)/4
18Price valid for a stated period ≥90 days (4) / 30 days (2) / open (0)/4
19Tooling ownership defined — you own it (4) / factory owns (1)/4
20Payment terms and currency risk addressed (3) / unclear (0)/3

Service — 15% (3 checks)

#CheckScore
21RMA response ≤48 h with replacement shipped (5) / ≤7 days (3) / none (0)/5
22Named technical contact with engineering access (5) / sales-only contact (2)/5
23EOL notice ≥12 months committed in writing (5) / 6 months (2) / none (0)/5

Scoring Three Realistic Suppliers

Supplier ASupplier BSupplier C
Unit price (200 W)$18.40$21.10$26.80
Quality (25)122124
Certification (25)102023
Delivery (20)111714
Commercial (15)12119
Service (15)61213
Total518183

Supplier A is cheapest and fails outright: no documented burn-in, unverifiable certificate. That is the normal shape of the result — the bottom-quote supplier usually scores lowest.

Supplier C scores highest and costs 46% more than A. Is it worth it? On a 5,000-unit order that is $42,000**. One percentage point of field failure on 5,000 units is 50 RMAs; at $180 labour plus 60 freight each, that is **12,000 — plus the account damage, which is the part nobody puts in the spreadsheet.

The correlation between price and score is strongest in the middle of the range. The most expensive supplier is often selling brand premium rather than quality; the cheapest is almost always selling a shortened process. Score the 2nd to 4th cheapest and pick from there.

How to Use It

  1. Send all 23 checks as your RFQ attachment. Suppliers who fill it in seriously have already separated themselves from those who do not.
  2. Score from documents first; re-score after a factory audit.
  3. Re-score annually. A supplier who scored 81 two years ago may have changed capacitor vendors.

Score us. Send the 23 checks and we will fill them in and return the sheet — including the burn-in log and the capacitor brand. → Request our completed scorecard · Get a quote

⚡Factory-Direct Sourcing Support

As a trusted LED power supply manufacturer, INERPOWER delivers rigid engineering quality and custom OEM/ODM solutions to worldwide B2B clients.

Inquiry for Industrial & Waterproof LED Power Supplies →

Popular Contents

Email Contact
TOP